All Crossrail TBMs in the Herrenknecht basket
Sep 2011
Shani Wallis, TunnelTalk
- Click on the logos to enter the websites of those who have opened the door for direct access and exploration
-
Major engineering and contracting companies engaged on the Crossrail project to November 2011
Hot!- Programme Partner – Transcend, a JV of:



- Project Delivery Partner – Crossrail Central, a team of:


Hot!
- CONTRACT PACKAGES
Contract Package description Engaged constructor C300 Running Tunnels West -
Royal Oak to Farringdon
C410
C435Bond Street and Tottenham Court
Road Station early access shafts works
Farringdon StationC305 Running Tunnels East -
Limmo Peninsula to Farringdon;
Limmo Peninsula to Victoria Dock;
Stepney Green to Pudding Mill Lane
C405
C330
C248Paddington Station
Royal Oak Portal Civils
Pudding Mill Lane Portal TBM
reception chamber
C510
C512Whitechapel and Liverpool Street
early access shafts and works
Whitechapel Station
Canary Wharf station delivery by
sub-partner Canary Wharf Group
C701 Instrumentation Monitoring
C200 Pudding Mill Lane - Site Facilities 
Hot!C210 Liverpool Street Station Advance
Works Package 2
C245 Whitechapel Station Civils,
Demolition & UtilitiesC240 Bond Street - Civils
C244 Whitechapel Station Civils 1 -
Steel Deck Over East London Line
C271 Paddington Integrated Project -
Advanced works
- DESIGN PACKAGES
Contract Package description Engaged firm C100 Architectural Component Design
C146 Custom House Station C102 Material & Workmanship Specification
C121 Sprayed Concrete Lining C124 Railway Systems & Tunnel M&E Services C131 Paddington Integrated Project C138 Liverpool Street Station C122 Bored Tunnels - Alignment & Track 
Hot!C134 Tottenham Court Road C123 Intermediate Shafts 
Hot!C130 Paddington Station
C136 Farringdon Station C152 Pudding Mill Lane C164 Bulk Power Distribution & HV System C132 Bond Street Station
C140 Whitechapel Station 
C154 Victoria Dock Portal C150 Royal Oak Portal
C156 North Woolwich & Plumstead Portal C170 Communications & Control System 
Hot!
- There it is, a clean sweep on Crossrail for Herrenknecht. Confirmation this week that the last two machines needed for the project's crossing of the Thames to the east of London have also been ordered from Herrenknecht brings a total of eight machines to be supplied by the German manufacturer for London's €14.5 billion mega railway project.
-
All eight TBMs for Crossrail on order with Herrenknecht
- The last two machines are slurry Mixshields ordered by the Hochtief/Murphy JV to complete the twin 2.6km drives under the Thames through fractured chalk that presents the possibility of operating under the full hydrostatic pressure of the river above. The contract is a repeat for Hochtief/Murphy of the river crossing it completed for the Channel Tunnel Rail Link (CTRL) in the early 2000s, also using Herrenknecht Mixshields. The slurry TBMs will launch from Plumstead Portal in late 2012 and drive westwards under the river to North Woolwich. Construction of the Plumstead Portal is now under way with work for the North Woolwich Portal commencing in early 2012.
- With the Thames machines, Herrenknecht will also deliver six EPB machines for working predominantly through London Clay between portals at Royal Oak in the west, Pudding Mill Lane at about mid point and Victoria Dock Portal to the east. Four of the machines are for the Dragados/J. Sisk JV for 8.3km of 6.2m diameter tunnels in three drives from Limmo Peninsula west to Farringdon, from Limmo Peninsula east to Victoria Dock, and from Stepney Green north to Pudding Mill Lane for the C305 Eastern Running Tunnels contract, and two are for the BAM Nuttall/Ferrovial Agroman/Kier JV for the 6.2km of twin 6.2m diameter Western Running Tunnels from Royal Oak to Farringdon for contract C300 (Table 1).
|
Table 1. Tunnel construction schedule
|
|
- facility for BAM Nuttall/Ferrovial Agroman/Kier will have 216 moulds to produce the 75,000 concrete segments needed to line the western running tunnels at a production rate of more than 200 segments/day at peak. The plant will employ about 50 people.
- At his presentation to the British Tunnelling Society last week (15 Sept, 2011), Mitchell explained that about 85% of the muck to be excavated by the project under the centre of London is to be transported by barges on the river and to a main disposal site on Wallasea Island in the Thames estuary. The rest will be moved by rail or road to land fill sites or facilities for secondary-use processing. Contract C807 for the river transport operation is currently out for bid, he said.
- At peak between 2013 and 2015, up to 14,000 people will be employed on Crossrail contracts.
-
Roll out of final tunnel contracts for Crossrail - TunnelTalk, March 2011
Herrenknecht lands central Crossrail TBMs - TunnelTalk, May 2011
Scheduling for success at Crossrail - TunnelTalk, April 2011
|
|
